Damages Claims in Property Development Disputes | JLN
×

Property development disputes can cause financial loss on several levels at once. A breach may delay the programme, increase borrowing costs, prevent the acquisition of a site or reduce the value of a development opportunity. The resulting claim can therefore be significantly more complex than simply recovering an unpaid sum.

At The Jonathan Lea Network, we advise developers, investors, landowners, property companies and special purpose vehicles (SPVs) on substantial damages claims arising from property development disputes. We act for claimants seeking compensation and defendants challenging whether the losses claimed were actually caused by the alleged breach or are legally recoverable.

A strong damages case requires more than a large spreadsheet. The legal basis of the claim, the counterfactual position, the evidence and the assumptions underlying any valuation must all fit together.

What Are Damages Intended to Achieve?

In a contractual claim, damages generally seek to put the innocent party, so far as money can do so, in the position it would have been in if the contract had been properly performed, subject to the applicable legal limits.

That does not mean every financial consequence of a dispute can be passed to the other party. The claimant must establish causation and satisfy rules concerning remoteness and mitigation. It must also prove the amount of loss with sufficient evidence.

In development disputes, this often requires a careful reconstruction of what would probably have happened if the breach had not occurred.

What Losses Can Arise in a Development Dispute?

Depending on the circumstances, a claim may include:

– lost development profit;

– diminution or reduction in land value;

– wasted planning, design or professional expenditure;

– additional finance and interest costs;

– refinancing costs;

– losses caused by project delay;

– increased construction or procurement costs;

– additional professional costs incurred because of the breach; and

– other consequential losses that satisfy the relevant legal tests.

Different heads of loss may overlap. The claim must be structured carefully to avoid double counting the same economic loss in different ways.

Lost Development Profit

Lost profit can be one of the largest and most contested elements of a development claim. A claimant may argue that, but for the breach, it would have acquired the site, completed the scheme and realised a particular profit.

The court will require evidence rather than an optimistic appraisal prepared for investment purposes. Relevant issues may include:

– whether planning permission had been obtained or was realistically achievable;

– the likely development programme;

– construction and infrastructure costs;

– development finance availability and cost;

– anticipated sales or rental values;

– affordable housing and planning obligations;

– market conditions during the relevant period; and

– the claimant’s ability and intention to carry out the project.

The earlier a project was in its lifecycle, the more uncertainty may need to be reflected in the assessment.

Expert valuation, accounting or development evidence may be required for substantial claims.

Diminution in Land Value

In some disputes, the appropriate measure may concern the reduction in the value of the land or asset rather than the profit from a hypothetical completed development.

For example, a breach affecting access, title rights or the ability to develop may make the land less valuable. The valuation may require comparison between the property’s value with and without the relevant problem.

The correct valuation date and assumptions can be contentious. We can work with specialist valuers to ensure that the expert analysis addresses the legal issue the court actually needs to decide.

Wasted Expenditure

A developer may have incurred planning fees, architects’ costs, surveys, legal expenses and other project expenditure before the transaction or development failed.

Some expenditure may be recoverable where it was reasonably incurred in reliance on the contract and has been wasted because of the breach. However, a claimant cannot generally recover the same loss twice by combining incompatible measures of lost profit and wasted expenditure without appropriate adjustment.

The purpose and timing of each cost should therefore be evidenced and linked to the relevant breach.

Additional Finance and Interest Costs

Delay can materially change development economics. A project that takes longer may incur additional interest, extension fees, refinancing costs or commitment charges.

A claimant must show that the additional finance cost was caused by the breach and was within the scope of loss for which the defendant can properly be held responsible. The finance documents and drawdown history may therefore be important evidence.

Defendants may challenge whether the financing was reasonable, whether the cost would have arisen anyway or whether the claimant could have taken steps to reduce the loss.

Delay and Increased Project Costs

A delay may lead to increased construction prices, professional fees, holding costs, insurance, security or other expenditure. It may also postpone sales or rental income.

These losses need a clear period of delay attributable to the breach. Where several events affected the project at the same time, causation can become complex.

Programme evidence, contemporaneous budgets and records of decisions taken during the delay can be important in distinguishing breach-related loss from ordinary development risk.

Causation: Did the Breach Actually Cause the Loss?

A claimant must establish a sufficient causal link between the wrongful conduct and the loss claimed.

This can be difficult in developments affected by multiple risks. A defendant may argue that planning would have failed, finance would not have been available, the market would have changed or another issue would have prevented the project from proceeding regardless of the breach.

The damages analysis should therefore test the alternative scenario rather than assuming that contractual performance would automatically have produced the forecast profit.

Remoteness and Foreseeability

Contract damages are also subject to rules that limit recovery for losses that are too remote. Broadly, the court considers whether the type of loss was within the reasonable contemplation of the parties in the relevant contractual context.

A highly unusual financing arrangement or exceptional downstream consequence may require particular scrutiny. The contract may also contain exclusions or limitations of liability that affect the recoverable amount.

We review the underlying agreement and the commercial context alongside the loss calculation.

The Duty to Mitigate

An innocent party is expected to take reasonable steps to reduce avoidable loss. This does not require it to take unreasonable risks or spend unlimited sums, but it should respond sensibly to the situation created by the breach.

In a development dispute, mitigation might involve seeking alternative finance, pursuing another purchaser, rescheduling work or considering a replacement site. Whether a particular step was reasonable depends on the circumstances at the time, not hindsight.

Defendants frequently raise mitigation arguments, so the claimant’s decisions should be documented where possible.

Expert Evidence and Valuation

Substantial development damages claims often require independent experts. Depending on the issues, these may include:

– property or development valuers;

– quantity surveyors;

– forensic accountants;

– planning consultants;

– finance experts; or

– construction delay experts.

Expert evidence in court is subject to procedural rules and the expert’s duty is to assist the court, not act as an advocate for the party instructing them.

We can help identify the appropriate discipline, frame the questions the expert needs to answer and ensure the evidence aligns with the pleaded legal case.

Defending an Overstated Damages Claim

A defendant should not assume that proving some breach means accepting the claimant’s financial model.

The claim may be challenged on causation, remoteness, mitigation, valuation assumptions or evidential gaps. It may also include losses that would have arisen even if the contract had been performed.

A focused defence can distinguish the underlying liability issue from the amount of compensation properly recoverable.

Documents and Evidence

Depending on the claim, useful evidence may include:

– the underlying contracts and variations;

– development appraisals and feasibility reports;

– planning documents;

– valuations;

– construction budgets and tender information;

– finance agreements and lender correspondence;

– sales or letting evidence;

– invoices and professional fee records;

– board papers and investment decisions; and

– contemporaneous correspondence explaining how the breach affected the project.

Earlier versions of appraisals can be important because they may show how expectations changed over time.

How We Can Help

Our team can assist with:

– identifying legally recoverable heads of loss;

– analysing causation and mitigation;

– reviewing contractual limits or exclusions;

– gathering and organising financial evidence;

– selecting and instructing appropriate experts;

– assessing lost profit and land value claims;

– challenging speculative or duplicated losses;

– negotiating commercial settlements; and

– pursuing or defending damages claims in court.

We also consider whether a different remedy, such as specific performance, better serves the client’s commercial objective where the disputed land or transaction remains strategically important.

Settlement of Development Damages Claims

A damages dispute can often be mediated before every valuation issue has been tried. The parties may use expert analysis and litigation risk to negotiate a commercial figure rather than incur the full cost of taking each disputed assumption to trial.

Part 36 offers and other settlement proposals may also have costs consequences in litigation and should be considered strategically. The court may additionally take into account an unreasonable failure to engage in alternative dispute resolution (ADR) when exercising its discretion as to costs.

Where several parties or claims are involved, a structured settlement can deal with payment, releases and future project arrangements together.

Frequently Asked Questions: Failed Property Development

Can I claim the profit I expected to make from the development?

Potentially, but the profit must be supported by evidence and the claimant must show that the project would probably have produced the relevant return but for the breach. Planning, finance, build costs and market evidence may all be important.

Can additional finance costs be claimed?

They may be recoverable in appropriate circumstances if they were caused by the breach and satisfy the relevant legal requirements. The financing arrangements and evidence of additional cost should be preserved.

Can I recover professional fees already spent?

Potentially, where the expenditure was reasonably incurred and has been wasted because of the breach. The relationship between wasted expenditure and any claim for lost profit needs to be considered to avoid double recovery.

Will I need an expert?

Not in every case, but substantial claims involving development value, lost profit, delay or complex finance frequently require independent expert evidence.

What if several different events caused the project loss?

The court will need to consider causation carefully. Evidence should distinguish the effect of the alleged breach from other planning, funding, construction or market factors that may have affected the development.

Speak to Our Property Development Damages Solicitors

Development losses can become difficult to prove if evidence is assembled only after positions have hardened. Early advice can help identify the correct measure of loss, preserve the relevant financial records and avoid unrealistic assumptions becoming embedded in the claim.

Contact The Jonathan Lea Network if a property development dispute has caused significant financial loss or you are defending a substantial damages claim.

For our wider services, see our Property Development Disputes Solicitors page.

Contact Us

We provide most enquiries with an indicative scope of work and fee estimate, based on the information you share. We aim to respond within one working day.

In the same email you will be invited to arrange a 20-minute complimentary, no-obligation video consultation, should the proposed scope of work and fee estimate be of interest. This initial discussion is designed to better understand your requirements, refine the scope and ensure our approach is fully aligned with your objectives, at the end of which we will email you a definitive formal fee estimate to consider and approve.

Where you would prefer to receive initial advice and guidance from the outset, or where a short introductory call would not be the most appropriate starting point, we may instead recommend a 2.5-hour fixed-fee appointment, starting from £700 + VAT. This enables us to review the information you provide, discuss your situation with you and provide considered, tailored advice at an early stage.

To make an enquiry, please email us at wewillhelp@jonathanlea.net, complete our contact form, or call us on 01444 708640.

Our Property Dispute Resolution Team

What Our Clients Say

Google rating score: 4.9 / 5, based on 99 reviews

Request a Free No Obligation 20 Minute Call

This introductory call is to discuss your matter so we can provide a well-considered quote.

 

However, please be aware that the free 20 minute call is at our discretion. If you are more looking for advice and guidance on an initial call, we may instead offer a one-hour fixed fee appointment instead.

 

Our fixed fee appointments are between £250 plus VAT to £350 plus VAT* depending on the complexity of the issues and seniority of solicitor taking the call

We provide enquiries with an indicative scope of work and fee estimate and offer a complimentary 20 minute phone or video call based on the information you share. We aim to respond within one working day.

Name(Required)
×
Get In Touch

Contact Us

In need of legal guidance? How can we help?

We provide enquiries with an indicative scope of work and fee estimate and offer a complimentary 20 minute phone or video call based on the information you share. We aim to respond within one working day.

Name(Required)